|
BASF-EOE/EG Capacity Upgrade Project
page 2 of 2
Power was supplied to the new unit by an existing 13.8KV
substation, which had to be shut down so that the new feeder raceway
and wiring could be installed – a process that required ISC
High-Hazard-Analysis Procedures. Chemical cleaning of oxygen
services instrumentation took place during this phase, as did wiring
of all designated “plant-trip” systems, grounding, and fiber-optic
installations.
Electrical
and instrumentation systems were installed on four towers during
phase two in an efficient, three-step process.As much work as
possible was done during step one while the towers were still
resting horizontally at grade. System installation was completed in
step two, after the tower had been raised to their final vertical
position. Tower electrical, instrumentation and heat tracing was
tied in to the EO/EG structure in step three.
The balance of phase two was devoted to installation of a
completely new electrical and instrumentation system to support EG
area upgrades, including new 600-volt switchgear sections (where ISC
high-hazard analysis procedures were again employed), new
motor-control centers, motor-power feeders, motor-control cables,
lighting, receptacles and instrument power wiring.
ISC
installed all instruments and vendor packages during this phase,
including all instrument wiring and process and pneumatic tubing, as
well as instrument mountings and related junction boxes and stands.
ISC concluded the work by connecting the new systems to existing
equipment in the EG unit control room and performing final system
checks.
This large, complex project was completed exactly as planned, one
time, within budget, and with one of the best safety records ever
recorded for a project of this size.
Back to page 1 |