|
BASF Aniline / MNB II Project
This project won an ABC Pelican Chapter Merit
Award and a Louisiana Contractor Merit Award in 2000.
BASF approved a $69 million expansion in 1998 at their Geismar,
Louisiana chemical plant that included new aniline and MNB plants,
as well as upgrades to the wastewater stripper and cooling tower.
Work spanned 21 months and concluded in July 2000. Total project
manpower peaked at 420 craftsmen from all participating contractors.
Engineering was executed by Kvaerner Process in Bridgewater, New
Jersey, and major construction contracts were awarded to various
civil and mechanical contractors.
Industrial
Specialty Contractors (ISC) was retained for electrical and
instrumentation work, along with process tubing and electrical power
for heat tracing. ISC also played an important role in the design
phase, and this was a key reason that the project was completed on
time, under budget and with no lost time accidents or recordable
injuries.
Work began with the owner and other participating contractors on
constructability and safety issues in August 1999 under a newly
adopted “Tier Two” construction services agreement with BASF. When
the project was complete, ISC associates had worked 78,449 man hours
on electrical and instrumentation, and an additional 17,126 man
hours on heat tracing. ISC manpower peaked at 115, with an average
of 62 workers on site throughout the project.
The
project was divided into four major work areas: the aniline unit,
MNB II unit, waste water stripper and OSBL (offsite construction).
Most construction took place in and near a 90-foot structure housing
a 180-ton reactor and MNB unit, both of which were additions to
existing process systems.
ISC’s work required nearly 80 miles of wire and cable, almost 3
miles of cable tray and 12 miles of electrical conduit. Instrument
air supplies alone required 8,610 feet of piping, and more than a
mile of process tubing was installed.
ISC received, checked and installed 476 field instruments, and
the project included more than 1,600 control loops, each of which
had to be checked before sign-off by the ISC and BASF field
technicians on the start-up team. ISC installed 676 light fixtures
with 85 lighting panels, plus associated disconnects, junction boxes
and transformers. ISC installed 27,000 feet of unistrut and angle
iron to support these systems. |