| |
CF Industries Reconfiguration II Project
This project was a merit award winner in the national ABC Eagle
Award competition in 1998. In addition it won an ABC Pelican Chapter Excellence
Award and was also cited by Louisiana Contractor Magazine as the
"best instrumentation/electrical" project of its size that year.
In September 1995, CF Industries, Inc., approved a $305 million
expansion of their Donaldsonville, Louisiana fertilizer complex.
This expansion included a fourth urea plant with granulation, a
third nitric acid plant, a second UAN solutions plant and additional
product storage and loading facilities. After the project was
approved, engineering contracts for the design of the new facility
were awarded to UHDE, GMBH in Dortmound, Germany; M. W. Kellogg
Company in Houston, Texas; and Salman and Associates in Baton Rouge,
Louisiana.
In March 1997, Kellogg Constructors, Inc. (KCI), the construction
division of the M. W. Kellogg Company, awarded Industrial Specialty
Contractors (ISC) a cost-reimbursable contract not to exceed $10.25
million for all labor, equipment, and supervision to perform 100% of
the electrical and instrumentation work, as well as all of the
process tubing and steam tracing.
ISC maintained an average workforce of 130 associates over the
15-month project duration, peaking at 252 associates. A total of
386,667 work hours were spent by ISC to complete the electrical and
instrumentation portion of this project, which ended in June of
1998.
As an integral part of the project construction team, ISC was
involved in the decision-making process for all major disciplines,
not just issues pertaining to the electrical and instrumentation
scope. The goal of the project team was to have a safe and
successful project. This team concept was the key to successfully
completing this project on time, under budget, with a quality
installation, and with a safety record that has set new standards
for construction at CF Industries, Inc. production facilities.
The project was divided into four major work areas: permanent
utilities and LAN System, offsite construction, power distribution,
and four new process units.
The installation of the permanent utilities and LAN System
included more than two miles of communication and fiber optic
cables, and 15,000 feet of 34.5 KVA high-voltage feeder cables.
The offsite construction included a new cooling tower with four,
2400-volt water pumps capable of cooling 85,000 gallons of water per
minute; a new automated rail car loading facility with its own
distributed control system (DCS); a new state-of-the-art radial
barge loader that eliminated the need for moving the barge during
loading operations; a new truck load-out facility with weigh scales,
a 40,000-ton UAN storage tank with inlet and outlet pumping stations
and a level control system; and 4,000 feet of conveying systems to
carry product to a new 23,000-ton urea warehouse and the barge
loading dock. Also required to support the offsite facilities were
local power distribution racks and a remote DSC I/O building.
Power distribution and operation control included a new
electrical substation with 34.5 KV switchgear, 5 KV switchgear,
600-volt switchgear, 480-volt motor control centers, variable
frequency drives, uninterruptible power supply (L/PS) systems,
emergency generators with automatic transfers, a fire detection
system, an interposing relay system and emergency shutdown system
along with transformers, power panels, disconnects, lighting
contactors and an HVAC system. Five I/O buildings were built to
accommodate the Honeywell TDC 3000 digital distributed control
system linked through a network of fiber optics to a new operation
control center that serves as the heart of plant operations.
The major portion of this project was the construction of four
new process units that are among the largest of their kind in the
world. They include a urea structure that stands just over 200 feet
in height to accommodate a 400-ton reactor, a granulation unit, a
UAN solutions unit, and a nitric acid unit. Combined, they accounted
for more than 950,000 feet of wire and cable installed in over
35,000 feet of cable tray and raceway and 168,680 feet of electrical
conduit.
ISC installed 1,105 light fixtures with 252 lighting panels,
disconnects, and transformers. Power and controls were installed
ranging from 2400 volts to 120 volts to supply 352 electrical
motors.
ISC also installed over 23,200 feet of piping for instrument air
supplies, 21,500 feet of process tubing and 31,000 feet of steam
tracing. ISC received, calibrated, and installed 4,350 field
instruments. More than 1,700 control loops were checked out and
turned over to the project start-up team, which included both ISC
and CFI field technicians.
ISC was responsible for the installation and check out of several
unique systems that included an instrument air drying system; a
sulzer compressor skid; Bauermeister roll crushers; ABB variable
frequency drives; Ronan nuclear level detection systems; Panametrics
ultrasonic metering systems; multiplex alarm systems; a deluge
system; two Frick refrigeration systems; Bently Nevada vibration
monitoring systems; and a Honeywell distributed control system.
The combination of these and many other unique systems makes the
CF Industries Product Reconfiguration II Project the largest, most
automated, and most productive nitrogen fertilizer production
facility in the world. |
|
|
|