Dow Chemical Company Mayflower EPDM Project
The Dow Mayflower project won the Pelican ABC Chapter Excellence in
Construction award and was runner up for the national ABC Eagle
award. It was also selected by Louisiana Contractor Magazine as one
of its "Best of 1997" Construction Projects.
The Mayflower EPDM Project at Dow Chemical's Louisiana Division
included the construction of a new processing unit, as well as
off-site modular construction consisting of 59 modules, a new
packaging and shipping facility, and the installation of a new flare
stack. ISC was awarded a
negotiated lump sum contract by the General Contractor, Performance
Contractors, Inc. to perform the instrumentation and electrical work
for the project.
The scope of ISC's work for the Mayflower EPDM Project consisted
of the complete installation of instrumentation and electrical
systems for the new processing unit and the new packaging and
shipping facility. ISC was also responsible for the installation of
temporary power systems for the project site and for the off-site
module fabrication yard.
Control Room Instrumentation The control room portion of the
instrumentation system included the installation of a DCS Mod-V
control system, a Bently Nevada vibration system, control room
junction boxes, cable tray, conduit, and interconnecting cables. ISC
was also responsible for all terminations, systems checkouts, and
loop check.
Field Instrumentation The field portion of the instrumentation
system included the field instrument calibration and installation.
Also included were the installation of field junction boxes,
instrument air piping, process tubing, nitrogen purge systems,
aluminum cable tray, rigid galvanized conduit, and instrument
cables. Instrument calibration and loop checks were included in this
work. The following is a breakdown of the items and the quantities
installed on ISC's portion of the project:
| Description |
Quantity |
|
| Instruments/Devices |
1,839 ea |
| Field Junction Boxes |
123 ea |
| Instrument Air Piping/Tubing |
23,000 ft |
| Process Tubing |
7,600 ft |
| Cable Tray |
4,300 ft |
| Conduit |
102,000 ft |
| Conduit/Tray Supports |
9,030 ea |
| 1/pr Instrument Cable |
380,000 ft |
| 24/pr Instrument Cable |
230,000 ft |
| Terminations |
59,800 ea |
| Calibration/Spec-Check |
3,045 ea |
| Loop Checks |
2,136 ea |
Electrical System Substation The substation portion of the
electrical system included work in 2 new substation buildings and
work in 2 existing substations. The substation work consisted of the
installation of grounding systems, transformers, switchgear,
variable frequency drives, motor control centers, cable tray, power
cable, and terminations. The following is a breakdown of electrical
items and the quantities installed for this portion of the project:
| Description |
Quantity |
|
| 13.8-4.16kv Transformers |
2 ea |
| 2.4kv-480v Transformers |
11 ea |
| 2.4kv Switches/Controllers |
44 ea |
| 480v MCC Vert. Sections |
81 ea |
| Bus Duct |
160 ft |
| Cable Tray |
120 ft |