Dow Chemical Company Mayflower EPDM Project

The Dow Mayflower project won the Pelican ABC Chapter Excellence in Construction award and was runner up for the national ABC Eagle award. It was also selected by Louisiana Contractor Magazine as one of its "Best of 1997" Construction Projects.

The Mayflower EPDM Project at Dow Chemical's Louisiana Division included the construction of a new processing unit, as well as off-site modular construction consisting of 59 modules, a new packaging and shipping facility, and the installation of a new flare stack. ISC was awarded a negotiated lump sum contract by the General Contractor, Performance Contractors, Inc. to perform the instrumentation and electrical work for the project.

The scope of ISC's work for the Mayflower EPDM Project consisted of the complete installation of instrumentation and electrical systems for the new processing unit and the new packaging and shipping facility. ISC was also responsible for the installation of temporary power systems for the project site and for the off-site module fabrication yard.

Control Room Instrumentation The control room portion of the instrumentation system included the installation of a DCS Mod-V control system, a Bently Nevada vibration system, control room junction boxes, cable tray, conduit, and interconnecting cables. ISC was also responsible for all terminations, systems checkouts, and loop check.

Field Instrumentation The field portion of the instrumentation system included the field instrument calibration and installation. Also included were the installation of field junction boxes, instrument air piping, process tubing, nitrogen purge systems, aluminum cable tray, rigid galvanized conduit, and instrument cables. Instrument calibration and loop checks were included in this work. The following is a breakdown of the items and the quantities installed on ISC's portion of the project:

Description Quantity

Instruments/Devices 1,839 ea
Field Junction Boxes 123 ea
Instrument Air Piping/Tubing 23,000 ft
Process Tubing 7,600 ft
Cable Tray 4,300 ft
Conduit 102,000 ft
Conduit/Tray Supports 9,030 ea
1/pr Instrument Cable 380,000 ft
24/pr Instrument Cable 230,000 ft
Terminations 59,800 ea
Calibration/Spec-Check 3,045 ea
Loop Checks 2,136 ea

Electrical System Substation The substation portion of the electrical system included work in 2 new substation buildings and work in 2 existing substations. The substation work consisted of the installation of grounding systems, transformers, switchgear, variable frequency drives, motor control centers, cable tray, power cable, and terminations. The following is a breakdown of electrical items and the quantities installed for this portion of the project:

Description Quantity

13.8-4.16kv Transformers 2 ea
2.4kv-480v Transformers 11 ea
2.4kv Switches/Controllers 44 ea
480v MCC Vert. Sections 81 ea
Bus Duct 160 ft
Cable Tray 120 ft