|
Exxon BAPP Line Eight Project
This
project was a national 1997 ABC Eagle Award winner for excellence in
construction.
The Baytown Polypropylene Plant (BAPP) Line Eight Project at
Exxon Chemical Company's Baytown, Texas facility consisted of an
addition to the existing polypropylene facility that created the
worlds largest single-train polypropylene plant.
ISC was brought in by Exxon
Chemical and the M. W. Kellogg Company at the early stages of the
project to address constructability issues concerning the electrical
and instrumentation portion of the project. ISC was awarded a fixed
and incentive-fee-based, cost-reimbursable contract by KCI, the
construction arm of The M. W. Kellogg Company.
ISC contracted to perform 100 percent of the electrical and
instrumentation work, as well as all of the process tubing and steam
tracing. ISC maintained an average workforce of 90 associates over
the 21-month duration of the project and peaked at 260 associates. A
total of 345,000 work hours were required to complete the electrical
and instrumentation portion of the project.
The project was divided into the five major tasks: site clearing
for the polymerization unit, which involved the relocation of
existing pole-line power; communication and fiber optic cables; the
demolition of an existing rail car facility and the construction of a
new facility; the addition of two new extruders and modifications to
the existing finishing building; construction of a new
polymerization unit; and an addition to the existing rail car
loading facility.
ISC's scope of work for the pole line relocation phase consisted
of rerouting existing medium-voltage power, phone, RTU communication
and fiber optic cables to facilitate the construction of the new
polymerization structure. This work had to be accomplished without
disrupting facility operations.
During this phase of the project, ISC also installed electrical
and instrumentation for the new rail car wash facility. Once the new
car wash was operational, the old facility was demolished to make
room for the construction of an additional rail car loading
facility.
The next phase of the project involved a major addition to the
existing five-story, 70-foot finishing building. Electrical work
included the installation of a new electrical substation with
transformers, switch gear and bus duct; underground conduit duct
banks; electrical cable tray and conduit systems; grounding systems;
medium-voltage and 600-volt motor feeders; area lighting; a
page/party system and an HVAC package system.
Instrumentation work included installation of a new I/O building
to house a new Distributed Control System, connections to the
existing DCS system with a fiber optic link, field instruments,
field junction boxes, home run cabling and cabling and conduit to
the field devices, instrument air piping, process tubing, loop check
and start up assistance. Also included in the instrument scope of
work was installation and check out of numerous complex specialty
systems. These included two Werner and Pfleiderer Extruder Trains, a
Bently Nevada monitoring system, a Forney DCS system, Henschel mixer
systems, pellet dryer systems, KTRON weigh scales and Matcom dump
systems.
The largest portion of the project was the polymerization unit.
The grass-roots portion included the installation of a new
electrical substation, a 13.8KV distribution system utilizing
conventional pole-line construction, underground duct banks,
electrical cable tray and conduit systems, bus duct, grounding
systems, medium-voltage and 600-volt motor feeders, area lighting, a
page/party system, an emergency evacuation system and electrical
heat tracing.
The instrumentation work included installation of a new remote
instrument enclosure housing a new distributed control system,
connections to the existing DCS with a fiber optic link, field
instruments, field junction boxes, home run cabling and cabling and
conduit to the field devices, instrument air piping, installation of
the analyzer building and its associated tubing, loop check and
start up assistance.
ISC also assisted in the installation and check out of the following
unique systems: the deluge system, the Tormont refrigeration skid
and the Sulzer compressor skid. Along with the electrical and
instrumentation work, ISC was responsible for process tubing and
steam trace systems that included tubing raceway, pre-insulated
supply and condensate tubing, and all line and vessel tracing.
The final activity involved the addition to the existing rail car
loading facility. This work included substantial modifications to
the existing infrastructure in the load-out area. The electrical
work consisted of medium-voltage and 600-volt motor feeder
installations, cable tray and conduit systems, area lighting,
grounding systems and a page/party system. Instrumentation work
consisted of home run cabling to existing field junction boxes,
field instruments, cabling and conduit to the field devices,
instrument air piping, process tubing, loop check and start up
assistance.
Overall BAPP Line Eight Project electrical and instrument work
included more than 980,000 feet of wire and cable installed in over
4,000 feet of cable tray and 255,000 feet of conduit. There were 780
light fixtures along with 21 lighting panels and transformers
installed on the project. ISC also installed over 16,000 feet of
piping for instrument air supply, 23,000 feet of process tubing,
4,000 feet of analyzer tubing and 21,000 feet of steam-trace tubing.
ISC also received, calibrated and installed over 2,200 field
instruments. More than 1,700 control loops were checked out and
turned over to the project start up team.
As an integral part of the project construction team, ISC was
involved in the decision-making process for all major disciplines,
not just issues pertaining to electrical and instrumentation. The
goal of the project team was the success of the total project, and
this team concept played a key role in successful completion of the
project on time, under budget, with a quality installation and a
safety record that set a new standard for construction at Exxon's
Baytown facility. |