Return to Welcome Page
     

PROJECT
PROFILES

 

 

ExxonMobil Pala Switch Condenser Replacement Project

This project won a national ABC Eagle Award in 2000, as well as an ABC Pelican Chapter Excellence Award. Louisiana Contractor Magazine also recognized the project as Louisiana's "best instrumentation/electrical" project of its size in 2000.

ExxonMobil (then Exxon Chemicals Americas) authorized a two-year, $57.4 million phthalic anhydride unit upgrade in January 1998. An additional $34.3 million was approved at that time for replacement of twelve switch condensers, related control room and emergency shutdown system upgrades and maintenance turnarounds on two reactors, two furnaces, an 8,000-horsepower compressor motor and a product finishing area. ExxonMobil elected to provide engineering services.

ISC was awarded a $4 million, cost-reimbursable contract in June 1999 for electrical and instrumentation work, including installation of process tubing and steam tracing. The job was completed six months later, in December 1999.

An average of 60 ISC associates was at work each day, but the project became far more demanding during the fast-paced turnaround phase, when as many as 220 ISC associates were on site. In just 50 days during this phase, ISC associates recorded more than 66,000 of the project’s 86,000 total man hours. Although the plant continued to operate and much of the work took place in highly congested areas, the project was completed with a perfect safety record, on time and under budget.

The rapid pace and congested work environment meant that cooperation and teamwork would be critical to safety. With that in mind, the project construction team encouraged frequent, active involvement. ISC responded with contributions in all major disciplines, not just those involving ISC’s electrical, instrumentation and steam-tracing work.

ISC planning was critical to the success of the project. More than 30 different systems were involved, and shutdowns could not take place concurrently because plant operations continued while the work was underway.

ISC solved this problem by scheduling work to coordinate with each system’s scheduled down time, and by stressing safety, quality, and productivity at every step.

Although the largest and most complex tasks involved demolition and replacement of a dozen switch condensers, the contract included six additional categories of work, including reactors, furnaces, finishing towers, a compressor, modules and a control room conversion.