|
ExxonMobil Pala Switch Condenser Replacement
Project
This
project won a national ABC Eagle Award in 2000, as well as an ABC
Pelican Chapter Excellence Award. Louisiana Contractor Magazine also
recognized the project as Louisiana's "best
instrumentation/electrical" project of its size in 2000.
ExxonMobil (then Exxon Chemicals Americas) authorized a two-year,
$57.4 million phthalic anhydride unit upgrade in January 1998. An
additional $34.3 million was approved at that time for replacement
of twelve switch condensers, related control room and emergency
shutdown system upgrades and maintenance turnarounds on two
reactors, two furnaces, an 8,000-horsepower compressor motor and a
product finishing area. ExxonMobil elected to provide engineering
services.
ISC was awarded a $4 million,
cost-reimbursable contract in June 1999 for electrical and
instrumentation work, including installation of process tubing and
steam tracing. The job was completed six months later, in December
1999.

An average of 60 ISC associates was at work each day, but the
project became far more demanding during the fast-paced turnaround
phase, when as many as 220 ISC associates were on site. In just 50
days during this phase, ISC associates recorded more than 66,000 of
the project’s 86,000 total man hours. Although the plant continued
to operate and much of the work took place in highly congested
areas, the project was completed with a perfect safety record, on
time and under budget.
The rapid pace and congested work environment meant that
cooperation and teamwork would be critical to safety. With that in
mind, the project construction team encouraged frequent, active
involvement. ISC responded with contributions in all major
disciplines, not just those involving ISC’s electrical,
instrumentation and steam-tracing work.
ISC planning was critical to the success of the project. More
than 30 different systems were involved, and shutdowns could not
take place concurrently because plant operations continued while the
work was underway.
ISC
solved this problem by scheduling work to coordinate with each
system’s scheduled down time, and by stressing safety, quality, and
productivity at every step.
Although the largest and most complex tasks involved demolition
and replacement of a dozen switch condensers, the contract included
six additional categories of work, including reactors, furnaces,
finishing towers, a compressor, modules and a control room
conversion. |