| |
ExxonMobil Plastics G-Line Project
This project won a 2004 ABC National Excellence
In Construction Merit Award , LA Contractor Magazine's Best
Electrical / Instrumentation Project of 2004 and an ABC Pelican
Chapter Award of Merit.

Baton Rouge, LA - On October 30, 2001, Industrial Specialty
Contractors, LLC (ISC) signed a lump-sum instrumentation and
electrical contract with Mitsui Engineering & Shipbuilding, Inc. and
ExxonMobil Chemical for a new “greenfield” plastics plant called
G-Line near north Baton Rouge, Louisiana, the first of its kind in
the world. The value of ISC’s work, including several related
contracts with other civil and mechanical contractors, totaled more
than $15 million.
ISC associates worked more than 300,000 hours on the project over
its 25-month life span. Their responsibilities included all
temporary power, underground electrical feeders, above-ground
electrical lines and instrumentation – including pneumatic tubing,
fiber optics and electronics in every part of the new plant – from
the poly area, tank farm, flare structure and cooling tower to the
multipurpose building, packaging & shipping, and all three
electrical substations. At its peak the project employed more than
220 ISC craftsmen.
Their work included 3 complete substations, along with all
transformers and supporting switchgear, bus duct, underground duct
banks, direct-buried cable, cable tray and conduit systems. ISC also
created a plant-wide grounding system, installed area lighting and
street lighting, and set up and connected an HVAC package. Emergency
notification and fire-alarm systems were also installed by ISC
craftsmen, as were15 lighting panels, 15 transformers and nearly 900
light fixtures.
The hub of ISC’s instrumentation work was a new I/O building
housing a new distributed control System (DCS) linked to the new
G-Line control room and back to the base plant via nearly half a
mile of fiber optic cable. More than 800 instruments were installed
and checked, a massive undertaking in its own right that required
completion and check-out of more than 2,400 loops.
Calibration and specification checks on all field devices were
also part of ISC’s work scope, along with all related cable tray,
conduit systems, and home-run and secondary cabling. ISC was
responsible for all loop checks and provided start-up assistance, as
well.
When their work was complete, ISC craftsmen had installed nearly
a million feet of wire and cable in almost 30 miles of conduit,
using nearly 20,000 feet of cable tray and 40,000 feet of support
material. The instrument air supply alone required more than 13,500
feet of piping, but ISC also installed 7,323 feet of process tubing;
13,814 feet of air-supply tubing; 5,619 feet of steam trace tubing
and 8,933 feet of analyzer tubing.
ISC retained two subcontractors for electrical testing of
equipment and cable and for scaffolds, Electro Test, Inc. and Brand
Scaffolding, but their work totaled just 2% of the contract’s total
value. ISC completed this enormous project without a single
lost-time safety incident, turning over the last of the new systems
eight weeks ahead of schedule. |
|
|
|