| |
ExxonMobil ROCC Phase I Re-Instrumentation Project
This project won an ABC Bayou Chapter Award of
Excellence in 2006.
Baton Rouge, Louisiana - The $2,150,000 ROCC Level 1
re-instrumentation project was completed in June, 2005, nine months
after two ISC teams mobilized at the ExxonMobil Refinery in October
of 2004. Altogether, the work required over 25,000 man-hours, 90
percent of which was self-performed. The contract reflected the
job’s “split personality,” with a lump-sum component for the more
predictable aspects of the work and a time and materials (T&M)
component for cutovers and other work that required more
flexibility.
Part of the work involved new construction and part entailed
modification of existing systems. Some activities were clearly
defined and scheduled in advance. Others were far less predictable.
ExxonMobil therefore decided to manage the work as two different
instrumentation and electrical jobs under a single contract. Each
required its own management staff, supervisors, coordinators, and
field craftsmen.
The ROCC (Refinery Operations Control Center) is the heart of
ExxonMobil’s 500,000 bbl/day operation on the banks of the
Mississippi in Baton Rouge. Because it monitors and controls
virtually every aspect of the 2,100-acre facility, its systems
connect hundreds of instruments on cracking towers, distillation
units, storage tanks and pipe manifolds separated by roads, bridges
and railroad lines. ISC replaced most of this complex system with
entirely new equipment, buildings, raceways and more than 3000
instrument loops to improve monitoring at four process units called
pipe stills 7, 8, 9 and 10.
The duration of ISC’s lump-sum work was expected to be six
months, and firm, staggered completion dates were set for each of
the four pipe stills. Among other things, lump-sum work included the
installation and start-up of two new, 65-foot remote instrument
enclosure (RIE) buildings to serve as termination points for more
than 356 miles of new, 144-core fiber-optic cables from the ROCC.
Each building required installation of independent power supplies
and controls.
Fiber-optic cables were routed from the ROCC to the two new RIE
buildings via galvanized, epoxy-painted, fireproofed cable trays
with tray covers, all of which were installed by ISC. From those two
buildings, 50-pair and 60-pair homerun instrument cables were routed
to more than 75 field-mounted junction boxes and four satellite
buildings within the pipe stills.
ISC’s lump-sum work continued inside the ROCC, where new
fiber-optic cable cabinets and patch cords were installed to receive
data from the fiber-optic field networks and distribute it to
displays and controls. Fireproofing of all conduits and cable trays
was included in designated areas within the pipe stills, along with
epoxy-painting of critical cable trays and scaffolding for all work
done at elevation.
ISC’s time-and-materials assignments revolved around the cutovers
from the old system to the new network. Each of the four pipe stills
was cut over in sequence as related lump-sum activities were
completed. This difficult, tedious work included the de-termination
of old cables and re-termination of more than 41,000 feet of new 50-
and 60-pair instrument cables in 75 field junction boxes and
satellite buildings. On average, each enclosure required 180 of
these terminations.
In addition to the cutovers, ISC installed nine new thermocouple
boxes, four new marshalling panels, four HPM cabinets, and 11 new
analog boxes, along with all associated wiring in the RIE structures
and satellite buildings. Due to security constraints and the
sensitivity of critical equipment, the T&M scope also included
testing, terminating, and fusion-splicing all fiber-optic cables in
the ROCC.
|
|
|
|