|
ExxonMobil Chemical Tank 771 Fire Recovery
Project
This project won
the 2004 GNOBR CICE Award, as well as an Award of Merit – Electrical /
Instrumentation from Louisiana Contractor magazine, and an ABC
Pelican Chapter Award of Merit.
Baton Rouge, Louisiana - A tank farm at ExxonMobil Chemical’s
Baton Rouge, Louisiana, refinery sustained substantial damage in
late September, 2003. Immediately after the fire, ExxonMobil signed
a $554,120 time-and-materials contract with Industrial Specialty
Contractors, L.L.C. (ISC) for the electrical and instrumentation
work necessary to supply temporary power and then bring the unit
back on line.
The work entailed identifying, documenting and replacing
electrical equipment, power lines and instrumentation, as well as
construction and installation of related structural supports and all
planning and coordination necessary to complete the work safely with
minimal disruptions in plant operations.
ISC’s work scope included labor, supervision, equipment and
materials for 100 percent of the electrical and instrumentation work
and related structural supports. ISC committed 15 associates to the
project full time for the entire four-month duration of the
assignment. When their work was complete in mid December 2003, ISC
associates had invested more than 11,070 hours in the job.
The first phase of the project focused on providing temporary
power to the burned-out tank unit so that affected plant operating
units could resume operations as quickly as possible. ISC began by
replacing a partially melted four-inch conduit carrying a 2,400-volt
feeder from the plant’s E-20 substation. A temporary switchrack was
then installed to route power to various critical loads.
Using CLX armored cable, ISC Associates then ran temporary power
lines to seven critical pumps and ten motor-operated valves (MOVs).
Another temporary feeder restored function to a security crash gate
during this phase. Because the fire had destroyed ExxonMobil’s
ability to monitor and control tank levels, temporary power was also
provided for the multiplexer and Varec junction boxes serving tank
gauging systems, control pumps and MOVs.
With temporary power on-line, ISC began field verification of all
conduit and wiring systems in the damaged area. Splice points were
identified and megged to existing loads to ensure that all systems
met current wiring specifications. A switch rack was constructed off
site, complete with all starters, breaker ties, buss boxes and
feeder conduits.
Once the new switch rack was installed, structural supports were
constructed to accept new cable tray and conduit for permanent power
and control wiring. ExxonMobil engineers decided that ISC’s
reconstruction work provided a good opportunity for control
upgrades, and ISC responded by reworking the aromatics multiplexer
cabinet to take advantage of modern fiber-optic technology.
To minimize conduit runs from instruments, a new instrument
junction box was added at the coalescer structure. Replacement
wiring was pulled to nine mixer motors, power supplies and controls,
including a PC cabinet and a mixer relay cabinet for remote control
systems.
A new south area control center (SACC) multiplexer cabinet was
added, along with input and output modules. Cable concentrators with
fiber-optic controls were installed in this cabinet for a new
control valve in the SACC raffinate feed line. Finally, new
2,400-volt controllers were installed on switch racks 13-5, P-71A
and P-71B.
In addition to all instrumentation, electrical and related civil
work for cable tray and conduit supports, ISC was responsible for
all scheduling, installation, pre-check and review of the testing
and commissioning procedures. The entire project was completed with
a perfect safety record. |