| |
Shell OP-II Revamp Project
This
project won the national ABC Eagle Award for excellence in
construction in 1996.
The OP-II revamp project at Shell Chemical Company's Deer Park
Facility consisted of work necessary to restart an existing ethylene
plant that had been idle for 14 years. Industrial Specialty
Contractors (ISC) was awarded a cost-reimbursable contract by the
general contractor, H. B. Zachary, to perform the instrumentation
work. One hundred percent of the instrumentation work was
self-performed by ISC with an average work force of 40 associates
over the 15-month duration of the project.
The scope of ISC's work consisted of installing a new distributed
control system, performing a total function check of this instrument
system, and executing a large cable installation, as well as
miscellaneous and off-site work. The distributed control system
included the installation of the control room consoles, work in the
remote instrument enclosure, a data highway between the remote
instrument enclosure and the consoles, field instruments, home run
cabling and raceway, field junction boxes, cabling and conduit to
the field instruments, instrument air piping, process tubing and
loop check.
The cable installation included a new electrical feeder to the
new OP-II motor control center. In addition, ISC installed the
emergency depression control system, pump seal pot tubing and
analyzer sample stations. ISC's off-site work consisted of a
metering skid, as well as work at the Deer Park Refinery Coker unit
and OP-II Unit plus the 9th Street pipe rack modifications. ISC was
also responsible for the safety management, planning, scheduling,
budgeting, cost control, quality assurance and bulk material
purchasing for all of these work activities.
The control-room portion of the distributed control included the
installation of consoles and cabinets, the connection of the data
highway and connections from the uninterruptible power supply
system. In the remote instrument enclosure, ISC installed or
assisted in the installation of the following systems: Honeywell TDC
3000, Triconex Shutdown Systems, Bently Nevada Vibration System and
Compressor Controls Corporation System. Other work included
installing interconnecting cabling and raceway, data highway cable,
other miscellaneous equipment and all of the control-room and remote
instrument enclosure cable terminations.
The first activity for the field portion of the distributed
control system work was the installation of the home run instrument
cables from the control room to the field junction boxes. This
installation consisted of some cable tray applications, but the
majority of the cables were pulled through rigid aluminum conduit
systems. The 34 home run cables averaged 700 feet each in length.
Additionally, ISC fabricated and installed the 10 junction box
racks and the 34 field junction boxes that were installed on the
racks. Aluminum conduit was installed from the field junction boxes
to each field instrument, and single pair and triad instrument wire
was pulled through the conduit from the field junction boxes to the
field instruments. ISC also provided air supply and process
connections to the field instruments and junction boxes. This work
included the installation of supports, angle iron and channel
raceway, copper tubing, stainless steel tubing, PVC-coated tubing,
tube valves, tube fittings, schedule 80 galvanized pipe ranging in
size from 2" to ½", pipe valves, pipe fittings and all associated
hardware.
The OP-II Revamp Project contained over 2,500 instrumentation
devices. ISC received, calibrated, stored and installed all of these
field instruments (including the stands to mount them on). Pre-loop
checks were performed on the system, then all of the 899 control
loops were checked and turned over to H. B. Zachary and Shell. ISC
also provided trained and certified personnel to operate the control
room consoles during this loop check phase of the project.
ISC installed approximately 5,000 feet of 250MCM, CLX 15KV cable
for the electrical feeders to the new 480-volt motor control center.
This cable installation consisted of four separate pulls in an
existing cable tray already containing energized cables and located
in elevated pipe racks. The 5,000 feet of cable came on four
separate reels, each weighing over 15,000 lbs.
This work was not in our original scope, but was assigned to ISC
because of our commitment to and track record for high-quality
installations. Also, this type installation is one of our
specialties, for which we have our own tools, equipment and skilled
associates with the necessary expertise.
The emergency compression control system consisted of installing
hand valves on a control station in the control room, approximately
10,000 feet of ½" stainless steel tubing, supports and tube tray.
The analyzer installations consisted of installing manual-type
sample stations, ½" stainless steel tubing and tube tray. For the
pump seal pot tubing, stainless steel tubing ranging from ¼" to ¾"
and supports were installed.
Several offsite projects were executed during the OP-II Revamp
Project. ISC removed and reinstalled instruments to facilitate
modifications to the 9th street pipe rack. The refinery coker unit
and OP-III unit work consisted of installing several instruments at
each location and performing the necessary connections and
modification to the control systems. At the process metering skid,
several instruments, a junction box, a PLC, omni and a satellite
were installed with all of the necessary connections.
As a member of the project construction team, ISC was involved in
addressing the situations and problems concerning safety, quality,
cost and schedule associated with this large "fast-track,"
schedule-driven project.
ISC's work force peaked at over 80 associates. Approximately
130,000 work hours were required, entailing total revenues of over
4.5 million dollars. The team concept was important in assuring the
successful completion of this project with an exemplary safety
record and quality installations, all without interruption of
adjacent operating units. |
|
|
|