|
Shell Norco Subsystems Project
This project won a 2004 ABC National Excellence
In Construction Eagle Award and an ABC Bayou Chapter Award of
Excellence.

Norco, Louisiana - No longer the relatively small chemical plant
it was in the 1950s, Shell Norco in 2003 had become a 1,000-acre
complex producing millions of pounds of ethylene and propylene,
aromatic and olefin feedstocks and methyl ethyl ketone (MEK).
Technology had changed enormously, and the huge plant needed a
complete re-instrumentation to replace old-fashioned pneumatic
instruments and controls with modern electronics and fiber optics.
ISC (ISC) mobilized in June,
2003, for the instrumentation and electrical work under an unusual
“common bare cost, fee at risk” contract with a total value of $5.6
million. Working under the direction of Shell Global Solutions, ISC
coordinated its activities with Shell Norco Operations and three
other major contractors. The Automation Group (TAG) provided
engineering and managed construction of the shutdown systems.
Yokogawa engineered and managed construction of the controls, and
Ford, Bacon & Davis did the mechanical work.
ISC’s work scope included multiple contracts with TAG and
Yokogawa for installation of new Triconex protective instrument
systems in the plant’s gasoline hydrotreater unit, butadiene unit
and olefins units. In addition, ISC installed new compressor-speed
and surge-control systems, replaced six recycle valves for three
process compressors and added new vibration transducer systems and
speed probes for five more compressors.
ISC replaced the plant’s Transmation thermocouple multiplexer
system and installed oxygen analyzers on thirteen furnaces. Two new
process analyzers were installed, and ISC upgraded and relocated the
plant’s Bentley Nevada vibration and temperature monitoring systems.
ISC crews pulled thousands of feet of multi-conductor instrument
cable and fiber-optic cable to link the plant’s many control rooms,
installing countless field junction boxes with the capacity for
future expansion. Altogether, ISC installed more than 385,100 feet
of wire and cable in 78,000 feet of conduit and completed more than
28,000 terminations.
In addition, ISC associates installed a new UPS system in a
prefabricated building and another UPS system in an existing motor
control center. They installed more than 1,500 loops, tied in the
new control systems with new distributed control system (DCS)
equipment, and were responsible for all commissioning and startup
work.
During the course of its work ISC coordinated its activities with
several contractors at work on other projects and managed three
important subcontracts, including Nolan Power Group’s UPS load
testing, the civil work done by Cajun Contractors to place the new
prefabricated UPS building, and all scaffolding done by Brand
Scaffold. In spite of the substantial scope of these subcontracts,
their value totaled less than 5% of ISC’s contract.
The workload was heavy throughout the 10-month life of the
project. Prior to the turnaround, ISC associates worked six-day
weeks. The schedule intensified to seven days per week during the
6-week turnaround. Once the turnaround was complete, ISC crews
worked five-day weeks until the project was complete. An average of
75 ISC field associates worked on the project, investing more than
116,000 man-hours between June, 2003 and project completion in
March, 2004.
|