|
Star Enterprise Division "A" Electrical
Substations
This project won the 1994 ABC Pelican Chapter Excellence Award.
Star Enterprise's Refinery in Convent, Louisiana manufactures
various grades of unleaded gasoline, diesel, avjet, kerosene, and
fuel oil. In a recent electrical upgrade, Star Enterprise replaced
the electrical substations for Division "A". ISC was awarded
lump-sum contracts for the entire construction portion of the
project, both the pre-turnaround and the turnaround phases.
The scope of the division "A" electrical substations project was
to construct and provide electrical power for two new 480-volt
substations, one new 2400-volt substation, and transfer all division
"A" electrical loads to these new substations. This scope was
accomplished by installing underground ductbanks with 500 CMC 15KV
feeders from the existing main substation number four to the three
new substations, installing new substation foundations, setting
equipment, installing downstream 480-volt ductbanks to existing
motor control centers and pull points, and transferring electrical
power from the old substations to the three new substations.
The 15KV ductbank from the main substation to the three new
substations consisted of installing four new 500 MCM 15KV feeders in
six-inch conduit encased in a red concrete and rebar envelope three
feet wide averaging five feet deep and running 2400 feet in length.
This ductbank crossed under a railroad spur, crossed two major
roads, and was installed in the centerline of a roadside ditch for
70 percent of the distance.
Six above-ground structural concrete pull points, each 9 feet by
18, were constructed in place and strategically located along the
ductbank. Steel covers, each four feet tall, were installed on the
pull points after the cable was installed. Approximately nine miles
of single-conductor 500 MCM 15KV cable was pulled through six
concrete-encased, six-inch conduits and pull points without any
splices between the main substation and the three new substations.
15KV terminations and cable testing were performed. Also, fiber
optic communication cables between the main substation and the three
new substations were installed, terminated, and tested.
Substation and transformer installations involved constructing
structural concrete foundations with drill shafts. Three
pre-fabricated, metal-clad substations weighing from 42,000 lbs. to
62,000 lbs., six transformers weighing from 11,000 lbs. to 35,000
lbs., and six 15KV switches were set on the foundations as they
arrived at the plant site. Electrical connections were installed
between the substations and transformers. Grounding was also
installed for the substation and transformer foundations.
The downstream portion of the project consisted of installing
480V and 2400V feeders from the three new substations to the
existing motor control centers and pull points in three different
operating units. This was accomplished by installing underground
ductbanks and overhead conduit banks with 25,000 feet of five-inch,
four-inch and three-inch galvanized steel conduit and 9.5 miles of
350 MCM 600V and 500 MCM 4KV cables.
The underground ductbanks were installed down unit alleys and
turned into the unit areas at various motor control centers and pull
points. Numerous pull-point and conduit stub-ups were constructed.
Three major road crossings were required that entailed concrete
pavement removal and replacement in all three units.
Many underground foundations and obstructions were encountered.
At the existing motor control centers, new structural steel racks
with foundations were installed and equipped with new main breakers.
Cable terminations were made at the three new substations and at the
new motor control center main breakers. Conduit and cable runs from
the new main breaker racks to the existing motor control centers and
from the new substation to various pull points were installed so as
to minimize electrical outages.
After the installation of 15KV feeders and substations were
completed, the three new substations were energized and tested.
During the division "A" turnaround, 25 motor control centers were
disconnected from the old substations and re-fed from the three new
substations. The cutovers were performed by connecting the new
feeders at existing pull points or at existing motor control
centers. This completed the downstream portion of the project.
ISC performed all of the work on the project, including
electrical, fiber optic, civil construction, ductbank installation,
setting equipment, and electrical cutovers. Coordination of
subcontractors was required to install steel casings under the
railroad spur, for cable testing, structural steel access platforms,
concrete saw cutting, and asphalt repairs. Star Enterprise furnished
all of the electrical commodities for the project. Extensive
coordination was necessary with the material supplier's agent to
ensure timely delivery of materials.
The division "A" electrical substations project required over
25,000 man-hours and cost $1,085,000 for electrical contracting
services alone. ISC performed the work in a rainy four- month span,
from December 1993 through March 1994, with a peak manpower level of
60 associates. ISC successfully completed this project in three
different operating units with a perfect safety record and on
schedule. |